AURECON AMEI LIMITED

Awards won
20
Known value
USD 26.2M
First award
15 Apr 2010
Most recent
29 Nov 2019

Wins by funder

FunderAwardsKnown valueMost recent
World Bank20USD 26.2M29 Nov 2019

Where the work is

KE · 1ZM · 1

Sources

The most recent award records behind the figures above. Every number on this page is computed from records like these — nothing is estimated or editorial.

  • Contract for the Engineering, Design and Supervision of Lusaka Transmission and Distribution Rehabilitation Project · 29 Nov 2019 · USD 3.9M · World Bank
  • Consultancy services for Implementation Support Consultants (ISC) for Water Resources Planning and Management · 11 May 2017 · USD 5.6M · World Bank
  • SAPP EAPP Study · 25 Apr 2017 · USD 829K · World Bank
  • Phases 3:Preparation of Conceptual Designs, Support in Procurement of Civil Works Contract and Monitoring Supervision Services for the Construction of Four Lanes Arterial Road from S.D. Cooper Road · 31 Mar 2016 · USD 797K · World Bank
  • Phases 1 and 2:Preparation of Conceptual Designs, Support in Procurement of Civil Works Contract and Monitoring Supervision Services for the Construction of Four Lanes Arterial Road · 31 Mar 2016 · USD 672K · World Bank
  • Consultancy Services for Conceptual Design and Preparation of Works contracts for Ganta to Zwedru appropriately 225.4 km using output and Performance Based Road Contracts (OPRC) under Design, Build a · 26 Feb 2016 · USD 1.6M · World Bank
  • Consulting Services for the overall Assessment and Optimization Study and Design of the Country's Hydro meteorological Network · 01 Dec 2015 · USD 1.1M · World Bank
  • Consultancy Services for Engineering, Design and Construction Supervision of the Lusaka Transmission and Distribution Rehabilitation Project (Phase 1) · 20 Nov 2014 · USD 1.0M · World Bank
  • Consultancy Services (Phase 2) for Engineering, Design and Construction Supervision of the Lusaka Transmission and Distribution Reha bilitation Project · 20 Nov 2014 · USD 4.1M · World Bank
  • Consultancy Services for preparation of Detailed Stragic Implementation Plan for the National Transport Master Plan Including the Greater Kampala Metropolitan Area · 19 Sept 2014 · USD 635K · World Bank
  • CONSULTANCY SERVICES FOR DEVELOPMENT OF CATCHMENT MANAGEMENT STRATEGY FOR SELECTED RIVER BASINS IN MALAWI · 30 May 2014 · USD 945K · World Bank
  • Works Supervision for Rehabilitation of Uige, Malanje and N'dalatando Water Supply Systems · 11 Apr 2014 · USD 908K · World Bank
  • Design Checking for Rehabilitation of Uige, Malanje and N'dalatando Water Supply Systems · 11 Apr 2014 · USD 123K · World Bank
  • PREPARATION OF NATIONAL INTEGRATED CATCHMENT MANAGEMENT AND RURAL INFRASTRUCTURE DEVELOPMENT GUIDELINES · 06 Feb 2014 · USD 72K · World Bank
  • PREPARATION OF NATIONAL INTEGRATED CATCHMENT MANAGEMENT AND RURAL INFRASTRUCTURE DEVELOPMENT GUIDELINES · 06 Feb 2014 · USD 826K · World Bank
  • SIERRA LEONE RESOURCE PORT SITTING OPTION STUDY. · 16 Jul 2013 · USD 250K · World Bank
  • TECHNICAL ADVISORY SERVICES FOR MORUPULE POWER PLANT CONSTRUCTION · 25 Apr 2013 · USD 1.1M · World Bank
  • Electrical Distribution System in the City of Luanda · 23 May 2012 · USD 462K · World Bank
  • Study on Regional Integration of Botswana’s Transport Sector · 08 Jul 2011 · USD 722K · World Bank
  • Consulting Services for preparation of Strategic Transport Master Plan for Rwanda · 15 Apr 2010 · USD 588K · World Bank

Method

Computed from 20 award records ingested from official disclosure sources (World Bank, Inter-American Development Bank, and published contract-award notices). Values are shown in USD where the source published one; entity identity is resolved conservatively and reviewed. GLODA is not affiliated with any funder or contractor shown. Last computed 15 Sept 2026.