Awards won
7
Known value
USD 3.5M
First award
11 Sept 2008
Most recent
13 Feb 2012

Wins by funder

FunderAwardsKnown valueMost recent
World Bank7USD 3.5M13 Feb 2012

Sources

The most recent award records behind the figures above. Every number on this page is computed from records like these — nothing is estimated or editorial.

  • CPC: package CPC-RD-KPak-W02 for Construction of 110kV Eakar - KrongPak line: from start point to G15 and feeder at 110kV Eakar substation · 13 Feb 2012 · USD 277K · World Bank
  • CPC: Package CPC-RD-KPak-W03 for Construction of 110kV Eakar - KrongPak line: from G15 to end point · 13 Feb 2012 · USD 361K · World Bank
  • PC3-110-CM-W02: Construction of Krong Buk - CuM'Gar 110kV TL · 02 Jun 2010 · USD 499K · World Bank
  • PC3-RD-CP-W02: Construction of Chu Prong 110kV line - section 1 · 08 May 2009 · USD 475K · World Bank
  • PC3-KP-W07: CONST. OF UNCOMPLETED WORKS OF KON TUM-KONPLONG 110KV LINE & 110 BAY AT KON TUM 110 KV SS · 08 Dec 2008 · USD 702K · World Bank
  • PC3-BC-W05: CONST. OF THE UNCOMPLETED WORKS OF BINH CHANH 110KV SS & BRANCH LINE · 08 Dec 2008 · USD 407K · World Bank
  • PC3-110-HT-W01: CONST. OF HOA THUAN 110KV SUBSTATION & BRANCH LINE · 11 Sept 2008 · USD 763K · World Bank

Method

Computed from 7 award records ingested from official disclosure sources (World Bank, Inter-American Development Bank, and published contract-award notices). Values are shown in USD where the source published one; entity identity is resolved conservatively and reviewed. GLODA is not affiliated with any funder or contractor shown. Last computed 07 Oct 2026.