ELC ELECTROCONSULT

Awards won
8
Known value
USD 29.5M
First award
01 Jul 2007
Most recent
18 Mar 2015

Wins by funder

FunderAwardsKnown valueMost recent
World Bank8USD 29.5M18 Mar 2015

Sources

The most recent award records behind the figures above. Every number on this page is computed from records like these — nothing is estimated or editorial.

  • Pre-Feasibility Study Update and Feasibility Level Design · 18 Mar 2015 · USD 4.1M · World Bank
  • TEAS for Rogun Hydroelectric Power Plant Construction project · 15 Sept 2013 · USD 3.7M · World Bank
  • Feasibility study for the 400 MW Menengai Phase 1 Geothermal Power Project and Associated Overhead Transmission Lines · 27 Aug 2012 · USD 922K · World Bank
  • Consultancy Services between Kenya Power & ELC for KEEP Transmission Component · 23 May 2011 · USD 5.3M · World Bank
  • Techno-Economic Assessment Study (TEAS) for Rogun Hydroeletric Power Plan Construction Project · 08 Feb 2011 · USD 6.4M · World Bank
  • SUPERVISION OF REHABILITATION OF UNITS 2 AND 3 OF HARTHA POWER STATION · 30 Apr 2008 · USD 2.5M · World Bank
  • ADVISORY SUPPORT TO HIGHER COUNCIL FOR PRIVATIZATION (HCP) FOR IMPROVING OPERATIONAL AND FINANCIAL PERFORMANCE OF EDL · 03 Sept 2007 · USD 2.3M · World Bank
  • ENGINEERING AND CONSULTING SERVICES FOR DOKAN AND DERBANDIKHAN EMERGENCY HYDROPOWER PROJECT · 01 Jul 2007 · USD 4.2M · World Bank

Method

Computed from 8 award records ingested from official disclosure sources (World Bank, Inter-American Development Bank, and published contract-award notices). Values are shown in USD where the source published one; entity identity is resolved conservatively and reviewed. GLODA is not affiliated with any funder or contractor shown. Last computed 07 Oct 2026.