Contractor intelligence · computed from public award records
SA-RA ENERJI
- Awards won
- 8
- Known value
- USD 38.5M
- First award
- 31 Dec 2008
- Most recent
- 30 Aug 2010
Wins by funder
| Funder | Awards | Known value | Most recent |
|---|---|---|---|
| World Bank | 8 | USD 38.5M | 30 Aug 2010 |
Sources
The most recent award records behind the figures above. Every number on this page is computed from records like these — nothing is estimated or editorial.
- HESCO ICB-03 (Lot I, VI, VII, VIII) - Procurement of 132 kV & 66 kV Allied Material and Line Material · 30 Aug 2010 · USD 116K · World Bank
- MEPCO ICB-6 Lot -II Proc of TL Material · 17 Aug 2010 · USD 32K · World Bank
- NTDC ICB-01R (lot-I) Procurement of 220kV Transmission Line Material for 220kV D/C Twin Bundle Two TL for F/F Kassowal Grid Station · 08 Jul 2010 · USD 166K · World Bank
- NTDC ICB-01R (Lot-II) Procurement of 220kV Transmission Line Material for 220kV D/C Twin Bundle Two TL for F/F Kassowal Grid Station · 08 Jul 2010 · USD 160K · World Bank
- Procurement of Grid Station Material (132 KV T/Line Hardware Material (Lot-I) & Grounding Sets Lot-III) ICB-09 Lot-I & III · 15 Jul 2009 · USD 335K · World Bank
- Supply and Installation of Facilities for the Electricity Distribution Networks Extension and Rehabilitation · 31 Dec 2008 · USD 16.2M · World Bank
- Supply and Installation of Facilities for the Electricity Distribution Networks Extension and Rehabilitation Package 3: (Meram 1.a - Konya II + Nigde II · 31 Dec 2008 · USD 9.9M · World Bank
- Supply and Installation of Facilities for the Electricity Distribution Network Extension and Rehabilitation Package 6: Ayedas-II (IAY VII) · 31 Dec 2008 · USD 11.5M · World Bank
Method
Computed from 8 award records ingested from official disclosure sources (World Bank, Inter-American Development Bank, and published contract-award notices). Values are shown in USD where the source published one; entity identity is resolved conservatively and reviewed. GLODA is not affiliated with any funder or contractor shown. Last computed 07 Oct 2026.